Grande Portage posts FAST-41 federal permitting schedule for New Amalga gold project in Alaska

PUBT · 2d ago
Grande Portage posts FAST-41 federal permitting schedule for New Amalga gold project in Alaska
  • Grande Portage posted a binding FAST-41 federal permitting schedule for its New Amalga Gold Project on the FPISC dashboard.
  • New Amalga entered FAST-41 on July 30, 2026, giving the project a coordinated federal review timetable with public milestone tracking.
  • U.S. Forest Service leads the federal permitting process; agencies must explain delays, reset deadlines, provide progress updates.
  • Project targets a small-footprint underground gold mine about 20 miles north of Juneau in the Tongass National Forest.
  • NI 43-101 resource totals 1,438,500 ounces indicated gold, 515,700 ounces inferred; plan calls for direct shipment of ore offsite.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Grande Portage Resources Ltd. published the original content used to generate this news brief via Newsfile (Ref. ID: 202609290400NEWSFILECNPR____20260929_316449_1) on September 29, 2026, and is solely responsible for the information contained therein.