Crusoe develops Google data center campus in Texas’ Armstrong County

PUBT · 12h ago
Crusoe develops Google data center campus in Texas’ Armstrong County
  • Crusoe will develop Google’s AI-focused data center campus in Armstrong County, Texas, outside Amarillo.
  • Project broke ground in June 2025; construction is underway with more than 5,500 workers on-site daily.
  • Campus will connect directly to Serena’s 265.5 MW Goodnight 1 wind farm; 265.5 MW Goodnight 2 is under construction.
  • Surplus wind power will be exported to the grid when generation exceeds campus demand.
  • Facility will use closed-loop, non-evaporative liquid cooling to limit water use mainly to domestic needs.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Crusoe Inc. published the original content used to generate this news brief on September 28, 2026, and is solely responsible for the information contained therein.