Nova Minerals says AIDEA authorizes up to $25 million for West Susitna access road work

PUBT · 1d ago
Nova Minerals says AIDEA authorizes up to $25 million for West Susitna access road work
  • AIDEA authorized up to $25 million to advance the West Susitna Access Road supporting Nova Minerals’ Estelle gold and critical minerals project.
  • Funding targets geotechnical drilling, permitting, engineering, hydrologic work, access preparations across the 2026/2027 field seasons.
  • Road plan covers 78.5 miles from near Alexander Creek to the Whiskey Bravo airstrip, linking into a separate 22-mile state project.
  • Geotechnical work progressed at material sites, Little Susitna River bridge testing, Susitna River bridge pier drilling; remaining in-river work slated May–July 2027.
  • Estelle access underpins a planned Port MacKenzie antimony refinery; phase 1 antimony trisulfide production backed by a $43.4 million DoW award.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Nova Minerals Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202609010630PRIMZONEFULLFEED9819272) on September 01, 2026, and is solely responsible for the information contained therein.