Harlan Electric completes Eversource New Hampshire S136 transmission line rebuild ahead of schedule

PUBT · 2d ago
Harlan Electric completes Eversource New Hampshire S136 transmission line rebuild ahead of schedule
  • MYR Group unit Harlan Electric completed Eversource New Hampshire’s 27-mile S136 115-kV transmission rebuild from Whitefield to Berlin.
  • Project scope replaced more than 200 wood-pole structures with light-duty steel, installed new 1272 ACSS conductor, added one OPGW line.
  • Harlan Electric self-performed drilling for more than 450 direct-embed foundations, supporting schedule control across shifting permit and outage windows.
  • Line construction finished in March 2026, months ahead of schedule; restoration work concluded in June.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. MYR Group Inc. published the original content used to generate this news brief on August 19, 2026, and is solely responsible for the information contained therein.