Nouveau Monde Graphite launches construction of Phase 2 Matawinie mine after C$427 million equity raise

PUBT · 2d ago
Nouveau Monde Graphite launches construction of Phase 2 Matawinie mine after C$427 million equity raise
  • Nouveau Monde Graphite confirmed the Phase 2 Matawinie Mine FID in Q2 2026, launching construction following a US$335 million debt commitment.
  • Equity financing package totaled C$427 million, including a May 15 private placement raising C$295 million; C$132 million in subscription receipts released.
  • Strategic framework with Canada set long-term take-or-pay covering 30,000 tonnes per year of flake graphite from Matawinie, with upside-sharing above a fixed price.
  • Phase 2 project spend reached C$33 million by June 30; committed costs totaled C$167 million; work remained within the overall budget.
  • Québec decree amendment lifted authorized annual graphite production to 106,000 tonnes from 100,000 tonnes, a 6% increase.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Nouveau Monde Graphite Inc. published the original content used to generate this news brief via Business Wire (Ref. ID: 202608130700BIZWIRE_USPR_____20260813_BW290286) on August 13, 2026, and is solely responsible for the information contained therein.