Hanking Gold wins Northern Territory clearance permit to start Mt Bundy processing plant site works

PUBT · 1d ago
Hanking Gold wins Northern Territory clearance permit to start Mt Bundy processing plant site works
  • Hanking Gold received Northern Territory permits to clear the processing plant site and begin mining activity at the Mt Bundy Gold Project.
  • Work started on site clearance; mining tenders launched while tender documents are prepared.
  • Project timeline targets processing plant construction in Q3 2026; first gold production in Q1 2028.
  • Mt Bundy holds 3.47 million oz of gold resources; 1.88 million oz of reserves under JORC (2012).
  • Environmental approvals cover underground mining in 2020; open-pit mining, processing plant, and infrastructure in 2023.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Hanking Gold International Ltd. published the original content used to generate this news brief via IIS, the regulatory disclosure system operated by the Hong Kong Stock Exchange (HKex) (Ref. ID: HKEX-EPS-20260724-12256560), on July 24, 2026, and is solely responsible for the information contained therein.