Abcourt Mines posts record Q4 development at Sleeping Giant gold mine, mill throughput jumps 160%

PUBT · 2d ago
Abcourt Mines posts record Q4 development at Sleeping Giant gold mine, mill throughput jumps 160%
  • Abcourt posted a Q4 operational update for the Sleeping Giant gold mine, showing a ramp-up in underground work through June 30, 2026.
  • Ore processed rose to 11,891 tonnes, up 160% quarter-on-quarter; June throughput hit 5,229 tonnes, a fiscal-year high.
  • Gold output totaled 720 ounces produced, 646 ounces poured; fiscal-year output reached 3,628 ounces produced, 2,647 ounces poured.
  • Underground development reached 554 meters, up 180% quarter-on-quarter; diamond drilling increased to 11,059 meters, up 155%.
  • Long-hole stope extraction started as the mine transitioned into stoping, despite lower processed grade of 2.1 g/t in the quarter.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Abcourt Mines Inc. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202607160700PRIMZONEFULLFEED9763109) on July 16, 2026, and is solely responsible for the information contained therein.