Salazar Resources says El Domo project after-tax NPV rises to US$573 million in SRK update

PUBT · 2d ago
Salazar Resources says El Domo project after-tax NPV rises to US$573 million in SRK update
  • Salazar Resources reported an updated NI 43-101 economic study for Ecuador’s Curipamba-El Domo project, lifting after-tax NPV at 8% to USD 573 million.
  • The NPV increase of 121% versus the October 2021 feasibility study reflects higher metal price assumptions despite lower reported resource grades.
  • After-tax IRR rose to 45% from 32% despite initial capital costs rising to USD 283.7 million from USD 248 million.
  • Proven and probable reserves increased 10% to 7.13 million tonnes, extending mine life to 13 years including roughly 1.5 years of construction.
  • Construction is fully funded, first commercial concentrates are expected in mid-2027, with a 25% carried interest through commercial production.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Salazar Resources Limited published the original content used to generate this news brief via Newsfile (Ref. ID: 202607150645NEWSFILECNPR____20260715_305197_1) on July 15, 2026, and is solely responsible for the information contained therein.