Tocvan targets Q4 2026 first doré from Gran Pilar 50,000-ton heap-leach pilot facility

PUBT · 2d ago
Tocvan targets Q4 2026 first doré from Gran Pilar 50,000-ton heap-leach pilot facility
  • Tocvan set a phased plan to start pilot-scale heap-leach mining at its Gran Pilar gold-silver project, targeting first doré pour in Q4 2026.
  • Build-out centers on a fully permitted 50,000-tonne heap-leach pilot facility intended to generate cash flow, validate metallurgy, de-risk commercial scale-up.
  • Major permits are in place, including a 10-year pilot mine permit secured in August 2025.
  • A 6-year community agreement signed in May 2026 is expected to support operational continuity, potential expansion flexibility.
  • Target heap-leach recovery is 70% gold, with pad construction progressing toward commissioning in Q3 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Tocvan Ventures Corp. published the original content used to generate this news brief via ACCESS Newswire (Ref. ID: 202607150205ACCESSWRNAPR_____1191104) on July 15, 2026, and is solely responsible for the information contained therein.