  • Cox won its first electricity transmission contract in Peru on November 24, 2026, expanding its Latin American presence.
  • The Belaunde Terry–Tarapoto Norte project in San Martín involves civil works and electromechanical installation, with completion expected in 12 months.
  • Work includes a new 220-kV Mayo substation with transformer capacity of up to 120 MVA, plus expansion of the Belaunde Terry substation.
  • A 220-kV double-circuit transmission line will connect the substations to strengthen regional electricity supply reliability.
  • The award follows projects in Brazil and Chile representing estimated investment of EUR 109 million and projected regulated revenue exceeding EUR 440 million.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Cox Infrastructure Group SA published the original content used to generate this news brief on November 24, 2026, and is solely responsible for the information contained therein.