From 18 GW to 52 GW! Goldman Sachs expects US AI infrastructure to accelerate until at least 2028 to set off an unprecedented “electricity bull market”

Zhitongcaijing · 4d ago

The Zhitong Finance App learned that although the construction process and licensing of large-scale AI data centers in the US may be significantly delayed after the Democratic Party wins the midterm elections, the content of a research report recently released by Wall Street financial giant Goldman Sachs extends the power capacity forecast for US data centers to 2028. It is estimated that 52 gigawatts (GW) will be added that year, close to three times the increase in 2026. If 52 gigawatts are put into operation as scheduled in 2028, it will set a new record for the largest annual electricity consumption of US data centers, about 3 times the increase expected by Goldman Sachs in 2026. In comparison, Goldman Sachs expects to add 18 and 28 gigawatts in 2026 and 2027, respectively. Previously, US data centers added an average of about 4 gigawatts per year from 2021 to 2024, and about 10 gigawatts in 2025.

Just as Goldman Sachs released this research report covering electricity capacity predictions, as of the close of trading on November 24, EST, Hwang In-hoon experienced a sharp drop in AI computing power and semiconductor prices in the global stock market triggered by Nvidia just one day later. On Monday, Nvidia rose 31.48%, and its market value increased by about US$952 billion in a single day, setting a record for single-day market value growth for listed companies in the US and the world. The strongest capital recovery on Monday was the Nasdaq 100 Index, which previously led the decline, with AI computing power and semiconductors holding the main market capitalization weight — the Nasdaq 100 Index rose 6.86%, and the cumulative market value of component companies rebounded by more than 2 trillion US dollars. In addition, the Philadelphia Semiconductor Index, which covered chip giants such as Nvidia and AMD, and the US-based memory chip giant Micron rose 14.03% and 19.04%, respectively.

However, by the close of the US stock market on Tuesday, the S&P 500 was down 0.50%, the Nasdaq Composite Index fell 1.48%, and the Philadelphia Semiconductor Index plummeted 7.88% to 8,832.50 points. Micron, AMD, and Nvidia were down 11.01%, 8.86%, and 5.86%, respectively. On Wednesday, sales pressure spread to South Korea and the entire Asian technology sector. The world's two largest memory chip giants, Samsung and SK Hynix, both fell more than 6% in early trading, and South Korea's KOSPI 200 futures fell 5.12%, triggering the Korea Stock Exchange to suspend the five-minute sell-side car mechanism for programmatic sales orders, and the spot market continued to trade.

After the US midterm elections, policy changes in places such as Texas, Ohio, and Georgia may slow down some large-scale data center projects that have not yet started. In the research report released on November 24, Goldman Sachs is still firmly extending the electricity demand expansion forecast to 2028. After reducing the project schedule according to historical delays and cancellations, it is expected that the US data center will add 52 gigawatts (GW) of maximum electricity consumption capacity that year, close to three times the estimated increase of 18 gigawatts in 2026. Of this, about 26 gigawatts had not started construction at the time of publication of the report. Whether data center power expansion capacity can reach this scale in 2028 largely depends on whether this batch of projects can be approved, started, and electrified on schedule.

18, 28, 52 gigawatts, why is the scale of large-scale AI data center construction in the US running faster and faster?

Goldman Sachs expects the maximum new electricity consumption capacity of US data centers to rise from 18 gigawatts in 2026 to 28 gigawatts in 2027, and then jump to 52 gigawatts in 2028. The increase in the number of computer rooms, the expansion of the area of a single building, and the increase in power density per unit area are jointly boosting power supply demand. Of the expected new capacity in 2028, about 35 gigawatts are concentrated in the three major electricity markets of PJM, Texas ERCOT, and Midwestern MISO, and about 26 gigawatts had not started when the report was released.

The key to this surge in power capacity is whether the AI server cluster can continue to be fully loaded after the project is powered on schedule. If the load rises as scheduled, electricity supply and demand in the core region will be further tightened, and the power generation and gas consumption of gas units are also expected to increase. This is an important bullish basis for Goldman Sachs to bullish the US Henry Hub gas price from 2028 to 2030 and is optimistic about the data center power equipment chain.

According to the Goldman Sachs analyst team, this year's actual increase has already surpassed the benchmark level of the past few years. By the end of October 2026, the maximum electricity consumption capacity of US data centers increased by 12 GW over the same period last year, an increase of 33%. Goldman Sachs estimates that this corresponds to an increase in average electricity demand of about 9 GW, more than double the average annual increase of 4 GW from 2022 to 2025. Compared with the US Energy Information Administration (EIA) national data as of August, data centers contributed more than one-third of the increase in electricity demand across the US. Among the three regional electricity markets, the capacity of PJM, Texas ERCOT, and Midwestern MISO increased by 4.4, 2.4, and 2.1 GW, respectively, over the same period last year.

image.png

image.png

Goldman Sachs expects to add 18, 28, and 52 GW of capacity from 2026 to 2028, respectively. It is estimated that an additional 10 GW will be added in 2025, with an average of about 4 GW per year from 2021 to 2024. Goldman Sachs will upgrade its capacity from 90GW to 92GW by the end of 2027, an increase of 44% over the end of 2026. Based on the annual increase in the report, the total capacity at the end of 2028 is approximately 144 GW.

Compared to 2026, the additional 34GW in 2028 came from three changes: more new buildings were put into operation, contributing 15.9 GW; higher power density per unit area, contributing 9.5 GW; and larger single building area, contributing 9.0 GW. Based on the calculation of all buildings already in operation, the average capacity of a single building will increase from 16 MW in 2020 to 31 MW in 2026. It is expected to reach 49 MW in 2028, and the average value of newly built buildings is even higher. Goldman Sachs expects that the average annual growth rate of single building area and power density will accelerate from about 6% each to 11% and 14%, respectively.

image.png

image.png

Half of the 52 gigawatts have yet to start construction. Where are the risks of commissioning concentrated

52GW is the project forecast after reducing historical cash out rates. Goldman Sachs began modelling the Aterio schedule in May 2026 to include projects that have already started construction, as well as projects that have met key conditions such as financing, licensing, grid agreements, land and water rights, and then reduced according to historical delays and cancellations. The Goldman Sachs model predicts that about 60% of the scheduled capacity will be put into commercial operation on schedule in the next 12 months, and about 50% over the next two years.

Based on a construction cycle of about two years, most of the projects to be put into operation before the third quarter of 2028 have already started. The scheduled capacity thereafter has reached less than half of the physical construction node. Based on the estimated operating capacity of the model, about 5 GW has not yet started construction in 2027, and it will rise to about 26 GW in 2028. This 26GW is within the 52GW forecast, which directly affects the 2028 fulfillment rate.

The expansion is still focused on the core electricity market. In 2028, Virginia and Texas are expected to contribute a total of 19GW, or about 36%, while PJM, ERCOT, and MISO will contribute a total of 35 GW, accounting for about 68%. As shown in the plan shown in the chart below, the total amount of unstarted capacity is limited nationwide in 2027, but the states of Florida, Kansas, Tennessee, and Arizona account for a relatively high share. By 2028, Texas, Virginia, and Arizona will have an unstarted capacity of about 6.4, 3.2, and 2.8 GW, respectively.

image.png

image.png

The risk may fall further into regional power grids. Of the expected capacity to be put into operation in 2028, PJM, ERCOT, and MISO will account for 55%, 45%, and 40%, respectively, while the Southwest Desert, Southeast Georgia, Northwest, and SPP will account for 68%, 55%, 73%, and 38%, respectively. Goldman Sachs believes that behind-the-meter power (Behind-the-meter Power), modular delivery, and faster construction can improve the payout rate. Policy changes after the midterm elections, as well as community resistance in Virginia, Arizona, etc., may increase delays beyond historical reduction rates. The following chart tracks the concentration of new capacity in the top states and regional grids.

image.png

image.png

How are 52 gigawatts transmitted to the data center power chain and gas and gas prices for power generation?

Goldman Sachs's natural gas benchmark originally only included 28 GW of new data center electricity consumption capacity per year. The 2027-2035 natural gas model assumes that the average electricity load brought by the data center will increase by 18 GW per year, equivalent to adding about 28 GW of maximum electricity consumption capacity each year, which is consistent with the Goldman Sachs stock research team's mid-term estimates. The 2027 schedule forecast is close to this benchmark, while the 2028 52 GW is significantly higher than the benchmark.

If the project is electrified on schedule and the load rises as the server is launched, regional electricity supply and demand will be further tightened, and there is room for improvement in gas consumption for power generation, which supports Goldman Sachs's excessive judgment on Henry Hub's natural gas price from 2028 to 2030. The following chart compares the two sets of predictions. The difference in historical values for 2025 comes from the data caliber of Aterio, S&P, and Lawrence Berkeley National Laboratories.

image.png

The overall forecast outlook in this Goldman Sachs research report explains to a certain extent why the AI computing power and semiconductor sector have plummeted and data center construction expectations have been delayed under heavy pressure from AI financing costs, yet electricity demand forecasts can still be improved. The topics of AI computing power and semiconductors are re-evaluated almost every day, while the fulfillment of power projects is determined by the unprecedented urgency of electrification, data center construction arrangements, grid connection, and equipment operation. For investors, the most recognizable developments are project commencement, implementation of power supply arrangements, actual power transmission to the computer room, and load rise. These nodes determine when the scheduled GW becomes the electricity sales volume for utilities, as well as the actual fuel consumption of gas-fired power plants.

image.png

AI training and inference workloads expand electricity consumption through different paths. Larger clusters and more experiments on the training side drive up the accelerator's installed scale and run time. The inference side depends on the number of calls, each task consumes tokens, and how many requests the server can process at the same time. Long inference and multi-round agent tasks may repeatedly call models, generate more tokens, and reduce concurrency efficiency. Chip upgrades, quantization, and batch processing can reduce energy consumption per unit of computation. Whether total electricity consumption is still growing rapidly depends on the increase in the number of tasks and the computational volume of each task, and whether it can exceed the reduction in energy consumption per unit.

From the chip to the meter, it is also necessary to go through two types of conversion: utilization rate and computer room loss. The data center supergrid system undertakes the entire station load of GPU, CPU, network, storage, plus cooling and power supply losses. According to Goldman Sachs, the maximum power consumption capacity is approximately equal to the power capacity of IT equipment multiplied by the efficiency of electricity usage (PUE). For example, a computer room with an IT capacity of 100 MW has an average IT load of 80 MW and a PUE of 1.2. The average load of the entire station is about 96 MW, and the annual electricity consumption is about 0.84 terawatt-hours (TWh). Therefore, 52GW is the answer to how much power supply capacity needs to be configured. The speed at which the equipment is installed, utilization rate, and actual number of runtimes will determine how much electricity is ultimately sold.