  • Horizon Gold has completed a Definitive Feasibility Study for its 100%-owned Gum Creek Gold Project, outlining a 10-year open-pit operation targeting 880,000 ounces of recovered gold.
  • Based on a gold price of $5,500 per ounce, Gum Creek is forecast to generate $1.85 billion in pre-tax free cash flow, with a projected pre-tax NPV of A$1.31 billion.
  • Horizon is targeting a Final Investment Decision in the June quarter of 2027, with construction potentially starting later that year and first gold targeted for the second half of 2028.
  • The project requires approximately A$350 million in pre-production capital expenditure, with Horizon appointing specialist adviser Orimco to manage a competitive financing process.

On Friday, Western Australian gold exploration stock, Horizon Gold (ASX:HRN), held its annual general meeting, providing an update on its progress towards becoming a gold producer.

The company has completed a Definitive Feasibility Study (DFS) for its 100%-owned Gum Creek Gold Project, outlining plans for a 10-year open-pit operation capable of producing an estimated 880,000 ounces of gold.

Horizon is now working towards a Final Investment Decision (FID) in the June quarter of 2027, with construction potentially starting later that year and first gold targeted for the second half of 2028.

Gum Creek outlines a sizeable gold mining opportunity

Horizon Gold released its feasibility study in July, which estimated a potential 880,000 ounces of gold recovered over a ten-year mine life, averaging around 98,000 ounces per year over the first five years.

Based on a gold price of $5,500 per ounce, the project is forecast to generate $1.85 billion in pre-tax free cash flow over its initial 10-year mine life. It also carries a projected pre-tax net present value (NPV) of $1.31 billion and an internal rate of return (IRR) of 53.1%, with an estimated payback period of 23 months from first production.

The project assumes an all-in sustaining cost of around $2,995 per ounce, suggesting that, assuming gold prices as projected, the operation could retain substantial profit margins.

It should be noted that these figures are projected figures based on assumptions, and that reality could differ significantly, which would change the economic viability of the mine.

The next steps of Horizon Gold’s Gum Creek project

Of course, being a successful mining stock requires more than a feasibility study.

Now that its definitive feasibility study is complete, the company is turning its attention to the practical steps required to bring Gum Creek into production.

Source: Horizon Gold (ASX:HRN) November 19 AGM presentation

The company is targeting a Final Investment Decision in the June quarter of 2027, with construction expected to begin in late 2027, subject to funding and approvals. While the approval processes have commenced, engineering work is also progressing.

However, financing will be a critical focus.

Horizon Gold estimates that the project will require around $350 million in capital expenditure before the mine produces anything. The company raised $30 million in March to fund exploration and other pre-development activities, and has around $16.9 million in cash at the end of December, so further financing is likely.

Horizon has appointed specialist adviser Orimco to manage a competitive financing process, with discussions underway to secure a suitable funding package. The eventual solution could involve debt, equity, or a combination of funding sources, although further equity issuance could dilute existing shareholders.

Is Horizon Gold approaching a key catalyst?

These next 12 to 18 months are likely to be an important period for Horizon as it looks to move from a gold exploration company towards becoming a gold-producing company.

Gum Creek provides a defined starting point, with a 10-year mine plan and scope for further growth through additional deposits and ongoing exploration. If the company can secure development funding and deliver the project as planned, it could establish a new revenue stream from late 2028.

Source: Horizon Gold past performance, Simply Wall St.

This can be seen by analysts forecasting revenue to start being generated in late 2028 or early 2029 calendar years, with potential earnings coming later in 2029. However, these projections remain dependent on Horizon securing the necessary capital, completing construction, and achieving its production targets.

For investors considering this small-cap ASX gold stock, the opportunity lies in what Horizon could become, while the risks remain firmly tied to what it still needs to deliver and how it can fund the items it needs to do to get there.

For Horizon, gold discovery is important, but getting Gum Creek into production could matter even more.

Disclaimer

This article was written independently by the author, without issuer input or approval. Horizon Gold has a marketing services agreement with Simply Wall St.