Nexans Completes Subsea Cable Installation for Chevron’s Jansz-Io Project

PUBT · 1d ago
Nexans Completes Subsea Cable Installation for Chevron’s Jansz-Io Project
  • Nexans completed subsea cable installation and burial for Chevron Australia’s Jansz-Io Compression project in October 2026.
  • The 145 kV dynamic cable spans approximately 135 km between Barrow Island and a floating control station.
  • Installation included 26 buoyancy modules; 30 km of cable was buried.
  • Cable connections and rock placement along the final 28 km remain outstanding before commissioning.
  • Chevron Australia plans the final energization test for February 2027.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Nexans SA published the original content used to generate this news brief on November 20, 2026, and is solely responsible for the information contained therein.