New Found Gold Presents Three-Phase Development Plan for Queensway Gold Project

PUBT · 19h ago
New Found Gold Presents Three-Phase Development Plan for Queensway Gold Project
  • New Found Gold outlined a fully funded plan to advance Queensway, with total funding of CAD 290 million.
  • Queensway Phase 1 requires CAD 150 million in capital; processing at Pine Cove is planned to start in the fourth quarter of 2027.
  • Pine Cove capacity is targeted to double to 1,400 tonnes daily by the second half of 2027.
  • A new Queensway mill is planned to begin operating in 2031 with capacity of 4,900 tonnes daily.
  • Queensway’s projected total gold production is 1.7 million ounces, with average annual all-in sustaining costs of USD 1,375 per ounce.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. New Found Gold Corp. published the original content used to generate this news brief on November 17, 2026, and is solely responsible for the information contained therein.