Lechwerke Starts EUR 2.9 Million Power Line Upgrade Between Gersthofen and Lechhausen

PUBT · 2d ago
Lechwerke Starts EUR 2.9 Million Power Line Upgrade Between Gersthofen and Lechhausen
  • LEW Verteilnetz began replacing conductors this week on the 110-kV transmission line between Gersthofen and Lechhausen, investing about EUR 2.9 million.
  • The roughly 10-kilometer line dates partly to the 1960s; some conductors have reached the end of their technical service life.
  • Higher-capacity conductors will replace existing cables, while towers, voltage and the route remain unchanged.
  • Work started south of Anwalting, with replacement proceeding west toward Gersthofen over the coming weeks before continuing south toward Derching.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Lechwerke AG published the original content used to generate this news brief on November 11, 2026, and is solely responsible for the information contained therein.