Dynacor Feeds First Ore to Ecuador’s Svetlana Mill
  • Dynacor expects delayed hot commissioning at Ecuador’s Svetlana plant in December 2026, with the first gold pour in January 2027.
  • Operations will start at 300 tonnes per day, ramping up to 500 tonnes per day in the first quarter of 2027.
  • Plant rehabilitation is 82% complete, remaining on budget against projected 2026 capital expenditure of US$22 million–US$25 million.
  • Spending totaled approximately US$10.7 million as of September 30, with another US$4 million committed.
  • First ore entered the crushing circuit at the end of October.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Dynacor Gold Mines Inc. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202611020730PRIMZONEFULLFEED9857530) on November 02, 2026, and is solely responsible for the information contained therein.